Projects

  Commercial Project - Capitagreen @ Market Street
   
Duration :2 Years
Fabricator :Yongnam Engineering & Construction Pte Ltd
 
HDG
Structure
:Column Beams, Truss-work & Roof Crown

 

     
     
  Recreational Project - Sportshub @ Kallang
   
Duration :3 Years
Fabricator :GTM Aluminium Pte Ltd
 Aik Lian Metal Glazing Pte Ltd
 Yongnam Engineering & Construction Pte Ltd
HDG
Structure
:Column Beams, Truss-work, Perimeter, Railings & Gates, General Road & Drainage Infrastructure
 
     
     
  Commercial Project - Carlton Hotel
 
Duration :2 Years
Fabricator
 
:Kong Hwee Iron Works & Construction Pte Ltd
 
HDG
Structure
:Column Beams, Truss-work, Perimeter & Railings
 
     
     
  Commercial Project - Asia Square Tower 1&2
   
Duration :4 Years (Total)
Fabricator :Yongnam Engineering & Construction Pte Ltd
 
HDG
Structure

:Column Beams, Truss-work & Railings, General Road & Drainage Infrastructure

 

     
     
  Residential Project - Le Nouvel Ardmore
 
Duration :2 Years
Fabricator
 
:Kong Hwee Iron Works & Construction Pte Ltd
 
HDG
Structure
:Truss-work & Railings, Perimeter & Gates, General Road & Drainage Infrastructure
 
     
     
  Residential Project - 368 Thomson
   
Duration :3 Years
Fabricator :Prime Structures Engineering Pte Ltd
 
HDG
Structure
:Perimeter, Railings & Gates, General Road & Drainage Infrastructure

 

     
     
  Commercial Project-Marina Bay Financial Centre (Mixed Development)
   
Duration
 
:5 Years (Total)
 
Fabricator :BHCC Construction Pte Ltd
 Steeltech Industries Pte Ltd
 Yongnam Engineering & Construction Pte Ltd
 Kong Hwee Iron Works & Construction Pte Ltd
 
HDG
Structure

:Column Beams, Truss-work, Perimeter, Railings & Gates, General Road & Drainage Infrastructure

 
     
  Commercial Project - Evonik Degussa @ Jurong Island
   
Duration :13 Months
Fabricator :PEC Ltd
 TTJ Holdings Ltd
 UTOC Engineering Pte Ltd
HDG
Structure

:Column Beams, Truss-work, Perimeter, Railings & Gates, General Road &Drainage Infrastructure

 
     
  Commercial Project - Lanxess Butyl Rubber Facility @ Jurong Island
   
Duration
 
:3 Years
 
Fabricator :PEC Ltd
 TTJ Holdings Ltd
 UTOC Engineering Pte Ltd 
 Unesis Engineering Pte Ltd
 
HDG
Structure

:Column Beams, Truss-work, Perimeter, Railings & Gates, Plant Piping Equipment & General Road & Drainage Infrastructure

 
     
  Iconic Project - Super Trees @ Gardens By The Bay
   
Duration :5 Years
Fabricator :TTJ Holdings Ltd
 
HDG
Structure
:Formwork of 18 Super Trees

 

     
     
  Iconic Project - Artscience Museum
   
Duration :5 Years
Fabricator :Yongnam Engineering & Construction Pte Ltd
 
HDG
Structure
:Column Beams & Truss-work

 

     
     
  Recreational Project - Southern Ridges & Henderson Wave
   
Duration :2 Years
Fabricator :TTJ Holdings Ltd
 
HDG
Structure
:Truss-work, Railings & Stairways

 

     
     
  Iconic Project - Esplanade & Theatres by the Bay
   
Duration :6 Years (Total)
Fabricator :Yongnam Engineering & Construction Pte Ltd
 
HDG
Structure
:Column Beams, Strutting & Truss Works

 

     
     
  Government Project - Parliament House
   
Duration :4 Years
Fabricator :Kong Hwee Iron Works & Construction Pte Ltd
 
HDG
Structure
:Column Beams & Truss-work

 

     
     
  ICA Project - Woodlands Immigration Center
   
Duration :3 Years
Fabricator :Kong Hwee Iron Works & Construction Pte Ltd
 
HDG
Structure

:Column Beams, Truss-work, Perimeter, Railings & Gates & General Road & Drainage Infrastructure

 

     
     
  Public Project - Changi General Hospital Extension Building
   
Duration :4 Months
Fabricator
 
:Ribar Industries Pte Ltd
 
HDG
Structure
:Underground Bored Pile Cages
 
     
     
  Public Project - National University Hospital Extension Building
 
Duration :3 Years
Fabricator
 
:Yongnam Engineering & Construction Pte Ltd
 
HDG
Structure
:Column Beams, Truss-work & Bracing, Railings & Stringers
 
     
     
  Contract Project - Keppel FELS Jack-ups & Semisubmersibles
 
Duration :On-going Term Contract Basis
Fabricator
 
:Keppel FELS Ltd
 
HDG
Structure
:All Piping & Deck Steel Works
 
     
     
  Retail Project - Seletar Mall
 
Duration :2 Years
Fabricator
 
:Kong Hwee Iron Works & Construction Pte Ltd
 
HDG
Structure
:Column Beams, Truss-work, Perimeter, Railings & Stringers
 
     
     
  MOE Project - ITE College Central
 
Duration :3 Years
Fabricator
 
:Kong Hwee Iron Works & Construction Pte Ltd
 
HDG
Structure
:Column Beams, Truss-work, Perimeter, Railings & Gates & General Road & Drainage Infrastructure
 
     
     
  Government Project - New Supreme Court
 
Duration :3 Years
Fabricator
 
:TTJ Holdings Ltd
 
HDG
Structure
:Column Beams, Truss-work, Perimeter, Railings & Gates
 
     
     
  MOE Project - Republic Polytechnic
 
Duration :4 Years
Fabricator
 
:Kong Hwee Iron Works & Construction Pte Ltd
 
HDG
Structure
:Column Beams, Truss-work, Perimeter, Railings & Gates & General Road & Drainage Infrastructure
 
     
     
  Retail Project - Funan Mall
 
Duration :1 Year 6 Months

Fabricator

:Topmast Engineering Pte Ltd


HDG
Structure

:Perimeter, Railings & Gates & General Road & Drainage Infrastructure
 
     
     
  Iconic Project - Jewel @ Changi Airport
 
Duration :3 Years
Fabricator :Yongnam Engineering & Construction Pte Ltd
 Topmast Engineering Pte Ltd
 
HDG
Structure
:Column Beams, Truss-work, General Road & Drainage Infrastructure
     
     
  Public Project - Sengkang General Hospital
 
Duration :2 Years
Fabricator

:Seng Choon Engineering Pte Ltd
 Choon Hin Stainless Steel Pte Ltd

 
 
HDG
Structure
:Chilled Water System Pipeline, Perimeter, Railings & Gates & General Road & Drainage Infrastructure.
     
     
  Residential Project - Marina One Residences
 
Duration :2 Years
Fabricator :Yongnam Engineering & Construction Pte Ltd
 
HDG
Structure
:Truss-work & Roof Crown
     
     
  Retail Project - Paya Lebar Quarter Mall (PLQ)
 
Duration :2 Years
Fabricator :Boon Chang Structure Pte Ltd
 GTM Aluminium Pte Ltd
 
HDG
Structure
:Column Braces, Truss-work, Perimeter, Railings & Stringers
     
     

 